NMBM installs water management valves to reduce consuption

Published: July 15, 2021

<< BACK TO NEWS
The Nelson Mandela Bay Municipality has embarked on a City wide pressure reduction (PRV) system installation to help achieve the much needed decrease in water consumption to prevent the dire situation of the City running out of water.

The combined levels of the main dams supplying the City are currently at just above 10 percent, with the level of our main supply dam, the Kouga Dam, declining rapidly to below 4 percent. 

The Kouga dam supplies the area of KwaNobuhle, one of the City's biggest townships, and the St Albans area, which has the St Albans Correctional Facility, accommodating more than five thousand prisoners.

The pressure management installations will contribute towards efficient water consumption, reduce water leaks and pipeline failures while assisting NMBM Water Services Department in controlling our water network and supply. It will also reduce the cost of maintenance and contribute to longer asset life.

Currently, 63 district metered areas throughout the City are already managed through PRVs. This equates to about 24 percent of the municipal water network. Additional sites have been identified, and more installations are currently underway.

Speaking at one of the sites where a PRV has been installed in Kabega Park, Mayoral Committee Member for Infrastructure and Engineering, Cllr Thsonono Buyeye, said that the PRV installation project was one of the more unpopular projects that the City had to accelerate in terms of implementation.

"Through this project, the residents will in some instances experience low pressure in their water supply. Although efforts are being made to decrease the impact as much as possible through targeting certain time frames, it is evident that some residents will be inconvenienced," said MMC Buyeye.

Buyeye said that the City was now racing against time to avoid situation of KwaNobuhle running dry.

A five kilometer pipeline is being installed to connect KwaNobuhle to the water system from Nooitgedagt. The project is expected to be completed by the end of August. The City has already started to install water tanks in KwaNobuhle to service the community should the area run dry.

Top stories


Vaccination drive underway to curb spread of Rabies in NMB September 16, 2021 In an effort to curb the further spread of the rabies virus in Nelson Mandela Bay, Mayoral Committee Member for Public Health, Cllr Lance Grootboom has urged residents to come out in numbers for the vaccinations of their pets.
Long awaited Helenvale sportsfields project completed September 15, 2021 Nelson Mandela Bay Municipality Portfolio Head for Sport, Recreation, Arts and Culture, Cllr Helga van Staaden today welcomed the completion and official handover of the new Helenvale Sportfields by the Mandela Bay Development Agency.
 

 

Using a Touch Screen?
Click below for instructions to fix Touch/Swipe issues experienced in Microsoft Edge.

Show me the fix! No thanks
This might take a while depending on your connectivity.
Please be patient while we search the entire site & all its modules for you...